Mexico Cerro de Oro Hydroelectric

Problem-Solving

Milestones and OA Actions

Date

Remarks

Request received by OA

11/30/2010

Incoming Request

Request acknowledged by OA

12/06/2010

 

Eligibility of request determined

12/20/2010

Requests from Santa Ursula, Paso Canoa, and Cerro de Oro communities deemed eligible

Assessment conducted

01/15/2011

Assessment visit determined that both parties willing to engage in problem-solving process

Problem-solving initiated

03/11/2011

March 11 Agreement English | Spanish
May 5 Agreement English | Spanish
July 20 Agreement English | Spanish

Problem-solving terminated

11/14/2011

Initial Problem-Solving Report English | Spanish
Final Problem Solving Report English | Spanish

Monitoring initiated

 

Since the parties did not reach final agreement, no monitoring was initiated

 

Compliance Review

Milestones and OA Actions

Date

Remarks

Request received by OA

11/30/2010

Incoming Request

Request acknowledged by OA

12-06-2010

 

Eligibility of request determined

12-20-2010

Requests from Santa Ursula, Paso Canoa, and Cerro de Oro communities deemed eligible

Assessment conducted

 

A separate assessment for compliance review was not necessary

Compliance review initiated

01-12-2011

 

Compliance review completed and parties notified

01-04-2012

Compliance Review English | Spanish

Management response issued

10-12-2012

OPIC Management Response

Monitoring initiated

 

Since the compliance review did not result in an audit, monitoring was not initiated.