Problem-Solving
| Milestones and OA Actions |
Date |
Remarks |
|
Request received by OA |
04/24/2008 |
|
|
Request acknowledged by OA |
|
|
|
Eligibility of request determined |
02/24/2009 |
Parties involved did not agree to participate |
|
Assessment conducted |
|
|
|
Problem-solving initiated |
|
|
|
Problem-solving terminated |
|
|
|
Monitoring initiated |
|
|
Compliance Review
| Milestones and OA Actions |
Date |
Remarks |
|
Request received by OA |
02/24/2009 |
Text of problem-solving request
|
|
Request acknowledged by OA |
05/30/2008 |
|
|
Eligibility of request determined |
|
|
|
Assessment conducted |
07/01/2008 |
|
|
Compliance review initiated |
09/01/2008 |
|
|
Compliance review completed and parties notified |
02/24/2009 |
Text of compliance review |
|
Management response issued |
02/24/2009 |
OPIC management response to Office of Accountability report |
|
Monitoring initiated |
|
|